SECTIONS
The Power Map · No. 06 — Amazon

One company, two names on the paperAmazon

The contract that put Amazon next to a nuclear plant is public because Talen filed it, not Amazon—a $650 million purchase agreement in which the buyer is Amazon Data Services, Inc., only $90 million buys the actual land, and escrow releases are pre-wired to zoning approvals at 540 and 960 megawatts (MW). The power went to a different Amazon: Amazon Energy LLC—which filed at the Federal Energy Regulatory Commission (FERC) for years under the shell name AZ721 LLC—signed the nuclear power purchase agreement (PPA), a fact disclosed in exactly one public document, an employee-bonus exhibit in Talen’s annual report. Amazon.com’s own U.S. Securities and Exchange Commission (SEC) filings never say “Susquehanna,” “Talen,” or “New Carlisle.”

When FERC rejected the expanded co-location deal—over its own chairman’s dissent—the order named Amazon once, as an intervener. The 2025 answer was a 1,920 MW contract through 2042, restructured so it “does not require FERC approval,” announced the same week as $20 billion for Pennsylvania beside Gov. Josh Shapiro—and eight days before Amazon’s chief policy executive wrote $25,000 to the Democratic governors’ Pennsylvania committee. Mississippi passed the $10 billion “Project Atlas” deal without the company’s name in the statute; Indiana’s regulator heard from two Amazon entities in one order. Every relationship on this page traces to a named public record, linked in The Record below; one line on the map is a labeled inference, and the method note says exactly what that label means. Records collected August 1, 2026.

$650M
Campus purchase · $90M allocated to the land
1,920 MW
Nuclear PPA through 2042
$10B
Mississippi’s statutory floor · company unnamed
$42,500
One executive → PA governor politics
1
Amazon mention in the FERC rejection order
0 of 104
Lobbying filings that name FERC
01—The networkdrag any node · hover a link to trace it · click to pin the source
CompanyData centerAgency / official / personPAC / committeeProceedingLobbying firmgovernment recordpartial support / labeled inference
How to read this map

Every line on this map is a documented connection drawn from a public record—Talen Energy’s own U.S. Securities and Exchange Commission (SEC) exhibits, a Federal Energy Regulatory Commission (FERC) order and its docket sheet, Federal Register notices, an Indiana Utility Regulatory Commission (IURC) order, Mississippi’s enrolled acts, Pennsylvania Department of State campaign-finance exports, Federal Election Commission (FEC) records, and Lobbying Disclosure Act (LDA) filings, collected August 1, 2026. Solid lines are contracts, orders, and filings in government records; dashed lines are attributions the record supports only partially. One dashed line carries the label INFERENCE: Amazon Energy LLC’s tie to Amazon.com, Inc. rests on the name and a market-based-rate docket trail—the same FERC docket filed for years under the shell name AZ721 LLC—and no registry or Amazon filing establishing parentage has been opened. An inference label means exactly that, and nothing more. A second dashed line, Amazon Data Services to Amazon.com, is supported by a notice clause in the purchase agreement but not by a registry record. Dollar figures on the links are the amounts in the cited filings. The map records documented connections, not allegations.

02—What this map meansone company, two names—and the disclosure done by others

What happened: Amazon built its power play on a two-entity split its own SEC filings never disclose. Amazon Data Services, Inc. bought the campus next to the Susquehanna nuclear plant—$650 million, of which only $90 million was allocated to the real property, with escrow releases pre-wired to zoning approvals at 540 and 960 megawatts (MW). Amazon Energy LLC—which filed at FERC for years under the shell name AZ721 LLC—signed the power purchase agreement (PPA), a fact that surfaces in exactly one public document—an employee-bonus exhibit in Talen’s annual report. Amazon.com’s own filings never say “Susquehanna,” “Talen,” or “New Carlisle.”

Who it moves: when FERC rejected the expanded co-location deal in November 2024—naming Amazon exactly once, as an intervener—the chairman dissented that the order was “a step backward for both electric reliability and national security.” The 2025 answer was a bigger contract built to need no FERC answer at all—1,920 MW through 2042, converted to front-of-the-meter, which Talen’s own investor material says “does not require FERC approval.” The ratepayer questions that co-location raised move with it. Meanwhile two legislatures moved the public’s side: Mississippi passed a $10 billion statutory deal in a two-day special session without putting the company’s name in the statute, and St. Joseph County, Indiana approved abatements a county official valued at roughly $1.9 billion net to the company—a press figure; the county agreement itself is a stated gap.

What it signals: this is the fifth anonymity structure on The Power Map, and it is the most institutional. Meta used one shell; OpenAI and Google used a developer’s; Microsoft rode an order that never named it. Amazon splits itself—one subsidiary for the land and the regulatory seats, one for the electrons—and lets counterparties do the disclosing. The political money matches the machine: the corporate PAC funds all four congressional campaign committees at the maximum and gives nothing to the House members whose districts hold its sites—except Rep. Michael Guest of Madison County, Mississippi, on a rising curve. The checks that land in decision windows are personal—the chief policy executive’s $25,000 to the Democratic governors’ Pennsylvania committee eight days after standing up a $20 billion deal with Gov. Josh Shapiro, and the AWS policy chief’s paired October checks into two theater delegations.

03—What each relationship meansmeaning first—the documented record sits beneath each one
Amazon Data Services → Berwick · The Purchase

The actual contract is public because Talen filed it: Exhibit 10.24 to Talen’s S-1, a Purchase Agreement for the “Data Center Campus, Berwick, PA.” The buyer is Amazon Data Services, Inc., a Delaware corporation. Price: $650,000,000—of which only $90,000,000 is allocated to the real property. The agreement carries a Rezoning Requirement Escrow with releases tied to zoning approvals meeting a “540 MW Requirement” and a “960 MW Requirement”—the expansion was pre-wired into the purchase, and a Talen employee-bonus exhibit keys staff payouts to those same escrow releases. Buyer notices route to Amazon.com, Inc. The deal closed March 1, 2024.

RECORD Talen S-1 Exhibit 10.24; Talen 10-K Exhibit 10.16. Closed Mar 1, 2024. · SEC (Talen exhibits)
Amazon Energy → Susquehanna · The Power, and the Shell Before It

The same day the campus closed, Susquehanna Nuclear, LLC—Talen’s plant subsidiary—“entered the Amazon Power Purchase Agreement and the Amazon Environmental Attribute Purchase Agreement with Amazon Energy LLC.” That sentence, in an employee-bonus exhibit, is the only public document naming the PPA counterparty. Amazon Energy LLC holds federal market-based-rate authority under FERC Docket ER15-1905—a docket that filed for years under the name AZ721 LLC. The April 2023 Federal Register notice carries both names on one filing; by May 2024 the applicant is simply Amazon Energy LLC. Its state of formation, officers, and address remain unopened—a stated gap, and the map’s one labeled inference.

RECORD Talen 10-K Exhibit 10.16; Federal Register combined notices, Apr 17 2023 and May 3 2024 (Docket ER15-1905). · SEC / Federal Register
FERC → ER24-2172 · The Rejection, Then the Workaround

In June 2024, PJM Interconnection, Susquehanna Nuclear, and PPL Electric asked FERC to raise the plant’s co-located data-center load from 300 MW to 480 MW. On November 1, 2024, FERC rejected the amended agreement (189 FERC ¶ 61,078). Chairman Willie Phillips dissented—“a step backward for both electric reliability and national security”; Commissioner Mark Christie concurred “without prejudice.” The order names Amazon exactly once, in the intervener list. The company whose load the fight was about is not a party on FERC’s paper. Seven months later came the workaround—a new PPA for 1,920 MW through 2042, converting to front-of-the-meter in Spring 2026—which Talen’s business update states “does not require FERC approval.” The 8-K names no Amazon legal entity at all.

RECORD FERC order Nov 1, 2024 (accession 20241101-3061); Talen 8-K Jun 11, 2025. · FERC / SEC
Indiana & Mississippi · The Other Two Theaters

In Indiana, the regulatory seat is held by the same entity that took title in Pennsylvania: Amazon Data Services, Inc. intervened and signed the settlement in IURC Cause 46097—the order requiring new large-load customers to make long-term financial commitments—while its witness testified from Amazon Web Services, Inc.: both entities in one state order. The campus itself, Project Rainier, is described in Amazon’s earnings exhibit as a collaboration with Anthropic to build “the world’s largest AI compute cluster”—with no location given in any Amazon filing; Amazon’s website places it in St. Joseph County. In Mississippi, the legislature passed a $10 billion statutory deal (“Project Atlas”) in a two-day special session—the statute never names the company; the state development agency’s release does: Amazon Web Services, Inc. Terms on paper—at least 1,000 jobs at 125 percent of the state average wage, clawback, a $260 million bond cap, $44 million cash, fee-in-lieu up to 30 years.

RECORD IURC order Feb 19, 2025; MS SB 2001 / HB 1 / HB 2 (2024 2nd Extraordinary Session); MDA release Jan 25, 2024. · IURC / MS Legislature
The money → the windows · The Personal Checks

Amazon’s PAC (FEC committee C00360354, filer name “Amazon.com Services LLC Separate Segregated Fund”) runs a flat institutional book—all four congressional campaign committees at $30,000 per cycle, both parties, zero nonfederal disbursements. The signature money is personal. David Zapolsky, Amazon’s Chief Global Affairs & Legal Officer as filed, gave $25,000 to the DGA Victory Fund—the Democratic Governors Association’s Pennsylvania committee—on June 17, 2025: eight days after the $20 billion Pennsylvania announcement with Gov. Josh Shapiro and six days after the 1,920 MW PPA. Then $15,000 more, and $2,500 directly to Shapiro for Pennsylvania, both in the governor’s 2026 reelection year—$42,500 in all, where Shapiro’s committee shows zero Amazon money before 2026. Shannon Kellogg, the AWS public-policy chief, wrote paired October 2025 checks to Rep. Michael Guest (MS-03, Madison County) and Banks for Senate (Indiana). The PAC funds Guest on a rising curve—$4,500 across the deal years—while giving nothing to the members whose districts hold New Carlisle or the Susquehanna campus. The filings record the donations; they do not record why.

RECORD PA DOS full exports 2024-2026; FEC Schedule A/B; verified absences stated. · PA DOS / FEC
The record’s gaps · The Absences

The absences are findings. Amazon.com’s SEC full text—zero hits for “Susquehanna,” “Talen,” and “New Carlisle”; “Rainier” appears only in earnings exhibits, never with a location. FERC appears in zero of Amazon’s 104 lobbying filings for 2025—a $17.78 million in-house program under the registrant name “AMAZON.COM SERVICES LLC,” with the only energy-coded work outsourced to Mindset Advocacy—$200,000 for “issues related to data center energy production.” Indiana’s state campaign-finance database contains no Amazon money at all—every “Amazon” row is a merchandise refund. Chief executive Andy Jassy’s personal giving touches no theater. Stated gaps, not papered over—the 2025 PPA’s Amazon signer entity, Amazon Energy LLC’s formation record, the Luzerne County deed, the St. Joseph County resolutions, the Mississippi fee-in-lieu signer, and Mississippi’s campaign-finance portal (blocked to automated search—a gap, not a verified absence).

RECORD EDGAR full-text; LDA filings 2025; Indiana bulk exports; FEC receipts. Searches verified Aug 1, 2026. · SEC / LDA / state databases
04—The split, traced
2023-04  AZ721 LLC / Amazon Energy LLC share one Federal Register notice2024-03-01  Campus closes ($650M); Amazon Energy signs the nuclear PPA2024-08-13  St. Joseph County approves the Rainier abatements2024-11-01  FERC rejects the co-location expansion; Amazon named once2025-06-09/11/17  $20B with Shapiro · 1,920 MW PPA · $25,000 to the DGA2026 (spring)  Front-of-meter conversion—no FERC approval required

The split was in place before the deals were. By April 2023 a Federal Register notice carried both names—AZ721 LLC, the filer of record, and Amazon Energy LLC, the company it had become—on one market-based-rate docket. On March 1, 2024 the two halves moved together: Amazon Data Services took title to the Berwick campus for $650 million (nine-tenths of it allocated to something other than the land), and Amazon Energy signed the nuclear power purchase agreement—a pairing disclosed only in Talen’s exhibits. That same winter Mississippi’s legislature had passed a $10 billion statute that names no company, and by August, St. Joseph County, Indiana had approved abatements a county official valued near $1.9 billion to the company.

Then the federal record said no, and the structure routed around it. FERC rejected the co-location expansion on November 1, 2024, naming Amazon once, as an intervener. Within eight days in June 2025, Amazon announced $20 billion for Pennsylvania beside Gov. Josh Shapiro, signed a 1,920 MW PPA running to 2042—restructured so that, in Talen’s words, it “does not require FERC approval”—and Amazon’s chief policy executive wrote $25,000 to the Democratic governors’ Pennsylvania committee. The conversion to front-of-the-meter lands in spring 2026. FERC appears in none of Amazon’s 104 lobbying filings for 2025.

SOURCES  Federal Register, Apr 17 2023 + 89 FR combined notice May 3 2024 (Docket ER15-1905) · Talen S-1 Exhibit 10.24 + 10-K Exhibit 10.16 (closing and PPA, 2024-03-01) · Inside Indiana Business / WSBT (county votes 2024-08-13; press figures) · FERC order 189 FERC ¶ 61,078, accession 20241101-3061 (2024-11-01) · Amazon release + PA DCED (2025-06-09) · Talen 8-K (2025-06-11) · PA DOS exports (Zapolsky, 2025-06-17) · Talen business update (front-of-meter, spring 2026)
05—The recordevery entry below names its primary document
The federal power record
Talen’s exhibits, FERC’s order, the Federal Register · collected August 1, 2026
Talen S-1 Exhibit 10.24 · the purchase agreement
Buyer Amazon Data Services, Inc. (Delaware) · $650,000,000, $90,000,000 to real property · zoning escrows at 540 MW and 960 MW · notices to Amazon.com, Inc. · closed Mar 1, 2024
Talen 10-K Exhibit 10.16 · the PPA counterparty
“Susquehanna Nuclear LLC entered the Amazon Power Purchase Agreement ... with Amazon Energy LLC” · employee payouts keyed to the zoning escrows
FERC order 189 FERC ¶ 61,078 · Nov 1, 2024
Docket ER24-2172 · rejects raising co-located load 300→480 MW · Phillips dissent, Christie concurrence “without prejudice” · Amazon named once (intervener)
Talen 8-K · Jun 11, 2025
1,920 MW PPA through 2042 · front-of-meter conversion, spring 2026 · “does not require FERC approval” · no Amazon legal entity named
Federal Register · the AZ721 trail
Docket ER15-1905 market-based-rate filings—applicant AZ721 LLC (2023) → Amazon Energy LLC (2024)

Every document in this column that names an Amazon entity was filed by someone other than Amazon. The purchase agreement, the PPA counterparty, and the shell-name trail are all in Talen’s and the government’s paper — Amazon’s own filings are silent.

Indiana & Mississippi
The state orders, statutes, and releases · collected August 1, 2026
IURC Cause No. 46097 · order Feb 19, 2025
Amazon Data Services, Inc. intervened (2024-08-08) and signed the settlement · witness from Amazon Web Services, Inc. · large-load customers must make long-term commitments
Project Rainier · St. Joseph County, IN
Amazon earnings exhibit—collaboration with Anthropic, no location in any filing · Amazon website places it in St. Joseph County · county abatements (press): 50%/10-yr + 85%/35-yr, ~$1.9B net
Mississippi “Project Atlas” acts · Jan 30, 2024
SB 2001: ≥$10B + ≥1,000 jobs at 125% average wage, clawback, $260M bond cap, 30-yr fee-in-lieu · HB 1: Project Atlas Fund · HB 2: $44M appropriation · the company is never named in statute
Who says it’s Amazon
Mississippi Development Authority—“Amazon Web Services, Inc.” · Governor’s groundbreaking release · Amazon’s own $25B statement (Apr 2026)

The Mississippi statute names no company; the Indiana order names two Amazon entities at once. The county-level paper (St. Joseph resolutions, Madison County fee-in-lieu) is not yet opened — stated as gaps, with press figures labeled as press figures.

Political money
PA DOS, FEC, and Senate LDA records · collected August 1, 2026
David Zapolsky → PA gubernatorial politics
$25,000 DGA Victory Fund Jun 17, 2025 (8 days after the $20B announcement) · $15,000 Apr 22, 2026 · $2,500 direct to Shapiro for Pennsylvania Apr 30, 2026 · $42,500 total · Shapiro’s committee shows zero Amazon money before 2026
Amazon PAC · C00360354
Filer “Amazon.com Services LLC Separate Segregated Fund” · $30,000 per cycle to all four Hill committees · zero nonfederal disbursements · nothing to Yakym (IN-02), Meuser (PA-09), or Bresnahan (PA-08) — verified absences
Amazon PAC + Kellogg → Rep. Michael Guest (MS-03)
PAC—$1,000 + $2,500 + $1,000 (2025–26, rising through the deal years) · Kellogg personal—$500 on Oct 9, 2025, paired with $500 to Banks for Senate (IN) Oct 21
Andy Jassy, personal
$5,000/yr to the Amazon PAC · only candidate giving this decade: Kaine and Cantwell (2023) · nothing in any theater
Amazon · federal lobbying, 2025
$17.78M in-house, registrant “AMAZON.COM SERVICES LLC” · ~$4.87M across 24 outside firms · only energy-coded work: Mindset Advocacy, $200,000, “data center energy production” · FERC in 0 of 104 filings

The map documents the donations, not their purpose. The DGA Victory Fund is the Democratic Governors Association’s Pennsylvania committee, not Gov. Shapiro’s own — stated plainly; the $2,500 of April 2026 is the only direct Shapiro receipt.

06—Agencies in this record (7) — the public bodies whose paper trail this page is built on
Federal Energy Regulatory Commission (FERC)U.S. Securities and Exchange Commission (SEC)Indiana Utility Regulatory Commission (IURC)Mississippi Legislature / Mississippi Development Authority (MDA)Pennsylvania Department of StateFederal Election Commission (FEC)St. Joseph County, Indiana

Get in touch

Good choice…

Thanks!

I’ll be in touch as soon as I can.